Supplier delivery notes can list quantities in cases while the warehouse counts individual units. Counts can be split across several receipts, and some goods can be held for inspection. To reconcile a shipment, you need to know which delivery-note lines account for which receipt quantities and which goods are still waiting for a decision.

Delivery note to goods receipt matching starts with three records. The purchase order (PO) authorizes what the warehouse can receive. The supplier’s delivery note or packing slip states what the supplier says was shipped. The goods receipt, sometimes called a goods received note (GRN), records a receiving transaction in the buyer’s system. Define which warehouse event counts as arrival, which transaction posts the receipt, and when goods become available. Those events can happen at different times.

Dynamics 365 illustrates the distinction. Workers can register arrivals, send goods through quality checks, and then post a product receipt. When posting, they enter a receipt identifier, typically the supplier’s packing-slip reference. Keep that external reference alongside the ERP’s internal receipt and line identifiers so an operator can trace the transaction in both directions. Microsoft Learn, Product receipt against purchase orders.

Capture the fields that identify a receiving line

Use the delivery note to find the shipment and the PO line or delivery schedule to identify the order commitment. Preserve original values alongside normalized ones. An operator should be able to tell whether a result came from a barcode, an ERP record, or characters read from a scan.

Where the data comes from Fields to keep What the match uses them for
Delivery note or electronic shipment notice Supplier account and site where available, note reference, shipment or notice ID, ship-to, source line reference, PO and schedule references, item code, quantity, unit, lot or serial where applicable Identify the supplier’s claim and point back to the line or pallet label
Purchase order and item master Company, supplier, receiving site, PO line and schedule, internal item, approved supplier-item mapping, base unit, pack conversion, order quantity, due date Identify the authorized line and put its quantities on a common basis
Warehouse and ERP receipt Arrival event, arrival time and site, count and unit, lot or serial where required, inspection disposition, ERP receipt and line IDs, posting time, corrections or reversals Explain what arrived, where it went, and what the ERP recorded

Treat supplier references as text. Preserve leading zeros and allow normalization only where the supplier’s reference format supports it. Scope reference lookups to the supplier and buying entity, and use the receiving site to narrow eligible order schedules. Two open PO lines can carry the same item. A description or SKU alone cannot establish which schedule the shipment belongs to.

For suppliers sending an advance shipment notice (ASN), retain the ASN line and, when used, the Serial Shipping Container Code (SSCC) from the pallet or other logistics unit. GS1 describes supplying the SSCC and the contents of each unit in the ASN, then scanning the label against that notice. A scan identifies the logistics unit. The receiving agreement determines when that scan suffices and when staff must open, count, or inspect its contents. GS1 Logistic Label Guideline, sections 9.3.7 and 9.5.

Allocate quantities across split receipts

Store the link at line level as a quantity allocation. A single delivery-note line may feed several receipt lines when goods are counted across shifts or separated by lot. A single receipt document may also contain lines for several POs. Dynamics 365 supports posting one supplier packing slip against more than one purchase order through a summary update. A header-level checkmark would hide unallocated quantities in either case. Microsoft Learn, Product receipt against purchase orders.

Use an approved conversion for the specific item and packaging to put each allocation in the same unit. Save the original quantity and unit, the conversion used, and the normalized quantity. Keep the conversion that applied when the shipment was processed so a later pack-size change leaves the earlier calculation reproducible. Hold an ambiguous pack code for review. Whole-unit items need an exact unit count, and measured goods need a declared precision and rounding rule.

Hypothetical example. A PO schedule calls for 120 units. Its first delivery note lists eight cases, with an approved conversion of 12 units per case. The dock counts 96 units across two unloading events. Receiving releases 90 units and holds six for inspection. The arrival count balances to the note, the inspection hold remains visible, and 24 units are still outstanding on the schedule if the ERP counts all 96 toward fulfillment. If it counts only accepted units, its open balance is 30 until inspection resolves the other six. Show which basis the ERP uses so a buyer can distinguish units still due from units already on site.

Give each tolerance a comparison and an action

The same variance can mean different things depending on what you compare. Define the two quantities or dates, the source of each, the unit and precision, and the action if the limit is exceeded. Record the rule that applied so a supervisor can reproduce the decision.

  • Delivery-note quantity versus dock count. For discrete items, begin with an exact comparison after conversion. If the dock count is short and unloading is complete, record the observed count and flag the difference. When multiple unloading events remain open, keep the note partially matched. A tolerance may govern who reviews a difference while the system preserves both quantities.
  • Receipt quantity versus PO authorization. Check cumulative net receipts plus the proposed posting against the authorized quantity on the relevant schedule and its over-receipt policy. Use the ERP’s own rules for how corrections and returns affect the balance. Check again at posting because another delivery may have used the remaining authorization. A split shipment can leave a valid open balance. Closing it short needs its own decision.
  • Arrival date versus scheduled date. Compare the warehouse’s local arrival date with the current agreed schedule date for the site. Preserve posting time separately so a weekend posting delay does not look like late delivery. Define the early and late windows separately and specify whether the calendar uses business or calendar days.

Oracle Fusion Cloud Receiving provides a product example. It documents a percentage over-receipt limit and separate early and late windows in calendar days. The configured action controls whether a breach is rejected, permitted with a warning, or permitted without a warning. Match the integration checks to the receiving policy enforced by the ERP. Oracle Fusion Cloud SCM, Receipt Creation.

A tolerance applies only after the shipment and schedule have been identified. A wrong receiving site, an unresolved item, or a missing required serial needs its own hold. Give receiving the dock count and source line, purchasing the schedule and open balance, and quality the lot and inspection record. Preserve the rule and the reason when an authorized reviewer clears an exception.

Keep document extraction separate from posting

Use structured shipment data when the supplier provides it. For paper and PDF notes, OCR or a document model can read references, quantities, and pack labels into candidate fields. Show the source excerpt beside flagged values. A missing PO line can produce a shortlist from eligible schedules, but a reviewer needs a way to confirm the allocation when several candidates remain.

Start by replaying historical notes against warehouse counts and ERP receipts with posting disabled. Include a repeated scan, a corrected note, a split delivery, a missing pack conversion, and a receipt later reversed. Compare the proposed receipt line and allocated quantity with the reviewed outcome. Track wrong links separately from cases sent for review. One false link can consume the wrong PO balance even when the document was read correctly.

If the workflow later writes receipts, key each posting to the warehouse receiving event and its approved allocation. A repeated scan of the same note should resolve to the existing document, while a genuine second unload can create a new receiving event. After a timeout, reconcile the event against the ERP before issuing another posting. Retain both the original transaction and any reversal so the warehouse and finance teams can reconstruct the balance.

The receiving integration and its posting rules belong in the ERP workflow. Insonl’s ERP Systems services.

The posted receipt is also an input to the accounts payable checks that compare the bill with the PO and the receipt. Insonl’s guide to three-way invoice matching.